Rudolph, KNDS Fuldatal
Project description
The new building with a total gross area of around 26,500 m², divided into three hall sections, will be used for an automated small parts and pallet warehouse, among other things. Two crane systems with a load capacity of up to 40 tons are used to load and unload trucks in the weather-protected interior of the hall.
Underground cavities and tunnels in a former lignite mining area posed a challenge that required a complex deep foundation consisting of approx. 22 km of concrete piles.
A photovoltaic system generates electricity, while heat generation is completely fossil-free.
Sustainability
- DGNB Gold
- E-charging stations
- ESG / EU taxonomy
- Heat pumps
- Rainwater utilization
- Insulated dock levellers
- Smart metering
- Photovoltaics
- Fossil-free heating